Change management communication plan with template
A change management communication plan defines which group receives which message, when, through which channel and from whom, from the first announcement until weeks after go-live. It builds on the stakeholder analysis and answers two questions that are often forgotten: who is the right sender, and how often does a message need to be repeated? According to Prosci, people want to hear the reasons for a change from leadership, but the consequences for their own work from their direct manager. A free template as an Excel file with an example is further down.
What goes into a communication plan?
A communication plan is a table, not a strategy on twenty slides. Each row is one message to one group. You need at least these columns:
| Column | Question | Example |
|---|---|---|
| Audience | Who needs to know? | Field sales, southern region |
| Purpose | What should the group know, want or be able to do afterwards? | Understands why visit reports move into the CRM |
| Message | What is the core in one sentence? | “So that before every visit you see what service and inside sales last discussed with the customer.” |
| Sender | Who says it? | Head of sales |
| Channel | How? | Regional meeting, then a short summary by email |
| Timing | When? | 10 weeks before go-live |
| Owner | Who prepares it and makes sure it happens? | Change manager |
| Feedback channel | Where do questions go? | Regional key user, shared mailbox |
The purpose column is the most important one and the one most often missing. It links the message to the stage a group is at right now. In the ADKAR model these are awareness, desire, knowledge, ability and reinforcement. A message meant to build awareness looks completely different from one that passes on knowledge. Putting both into the same circular email usually achieves neither.
Leadership explains the why, managers explain the impact
The sender decides whether a message is taken seriously. In its Best Practices in Change Management research series, Prosci asked from whom employees want to hear which information. The result is clear and summarised in an article on why some communications work and others do not1:
| Type of message | Preferred sender | Typical content |
|---|---|---|
| Business reasons | Senior leadership, sponsor | Why are we changing? What happens if we do not? How does it fit the direction of the company? |
| Personal impact | Direct manager | What changes for me and my team? What is expected of me? Where do I get help? |
| Content and dates | Project team, key users | When is the training? How does the new process work? Whom do I ask? |
In practice the project team often sends everything because it knows the content. That is convenient and weak. A circular email from the project team on “why are we doing this?” does not carry the weight of an explanation by the managing director in a town hall. And only someone who knows the team can answer “what does this mean for me?”. So the project team drafts, the managers speak.
This leads to a task that is easily overlooked: managers need their messages before their team does. A short briefing with the most important questions and answers, one week before the team meeting, turns a hesitant manager into a credible one.
How do you build a communication plan?
- 01
Take the groups from the stakeholder analysis
Every highly affected group gets rows of its own. Groups with high influence and little impact are informed selectively.
- 02
Write the key messages
One change story for everyone on why something changes, and one or two sentences per group on what changes for them.
- 03
Define senders and channels
Reasons from leadership, personal impact from the manager, content from the project team. Personal channels for sensitive messages.
- 04
Plan backwards from go-live
When does which group need to know what? Plan key messages several times, across different channels.
- 05
Set up feedback and adjust
Collect questions, add frequent ones to the next message, adjust the plan when a group does not follow.
A communication plan is a living document. If the same question keeps coming back after an announcement, the answer belongs in the next message, and perhaps a row is missing for a group you underestimated. The basis for this is the stakeholder analysis.
Example: communication plan for a CRM rollout
For introducing a CRM system such as Salesforce in sales, an extract could look like this. Weeks count backwards from go-live:
| Week | Audience | Purpose | Message | Sender | Channel |
|---|---|---|---|---|---|
| −12 | Everyone in sales | Awareness | Why we introduce one shared CRM and what happens otherwise | Managing director | Town hall |
| −11 | Sales managers | Desire | Your role, your questions, your messages for the team | Sponsor | Briefing |
| −10 | Field sales | Awareness | What changes for visit reports and forecasts | Regional head of sales | Regional meeting |
| −8 | Works council | Awareness | Which reports the system allows and which it does not | Sponsor | Meeting |
| −4 | Inside sales | Knowledge | New quoting process, training dates | Project team | Email and intranet |
| −2 | Everyone affected | Knowledge | What happens on go-live day, whom to ask | Key users | Team meeting |
| +2 | Everyone affected | Reinforcement | First successes, most frequent questions, what we improve | Head of sales | Team meeting and email |
Notice how few rows come from the project team, and that communication does not end at go-live. The message in week +2 is one of the most important: in this period morale and productivity often drop, as the change curve describes, and visible successes help people through the valley.
A global rollout adds another dimension. When countries in the US, Asia and Europe are involved, as in a Salesforce Sales Cloud rollout I supported, every country needs its own senders in its own language. A message from headquarters in English does not replace the country manager explaining why in their own meeting.
Communication plan template
The template as an Excel file contains an empty table with all columns from this article and the example from above. It is built so that you can take the groups straight from the stakeholder analysis template.
Which mistakes happen in change communication?
- Too late. Communication starts two weeks before go-live and can then only inform. Awareness and desire take weeks, not days.
- One sender for everything. The project team sends everything, the managers stay silent. To the team it looks as if they do not support the change.
- Content without reasons. Training dates and instructions without an explanation of why something changes answer the wrong question.
- No feedback channel. If questions have no place to go, they end up in the kitchen and come back as rumours.
- Silence after go-live. The hardest phase only starts after go-live. Going quiet then leaves the interpretation to those who are unhappy.
Salesforce programmes with regular releases need a form of their own: every new version changes something for a business team and needs a short, targeted announcement. Fabian Kramer describes how that works in Communicating Salesforce releases to the business.
Support pays off when many groups and countries are affected
For a change affecting one team, the template is enough. When many groups and countries are affected, when sensitive messages are due or when managers are unsure themselves, an outside view helps to sharpen messages and prepare managers. In Salesforce programmes I work with Fabian Kramer on this, see Salesforce change management consulting and Salesforce change management: why rollouts fail.
Prosci and ADKAR are registered trademarks of Prosci, Inc.
Sources1
Frequently asked questions
What is a communication plan in change management?
A communication plan is an overview that defines for every affected group which message it receives, when, through which channel and from whom. It accompanies a change from the first announcement until after go-live.
What should a change management communication plan include?
At least audience, message, sender, channel, timing and owner. The purpose of each message, such as building awareness or passing on knowledge, and a way to ask questions are also useful.
Who should communicate change in an organisation?
The reasons for the change are best explained by senior leadership or the sponsor. What changes for a team is explained by its direct manager. The project team supplies content and dates.
How often should a change be communicated?
Prosci recommends repeating key messages five to seven times, through different channels and senders. Something said only once does not reach most people.
What is the difference between a communication plan and a change story?
The change story is the one narrative of why something changes and where it leads. The communication plan defines how this narrative and the messages per group are spread over time.